I am attempting to simulate a compacted highway embankment in FLAC3D following the general framework for unsaturated hydro-mechanical behavior of compacted fill. My workflow involves staged construction of the embankment in lifts and eventual coupling with unsaturated flow.
During lift activation (especially when assigning MCC or shortly after), I repeatedly encounter: “Cam-clay: Yield envelope cannot be reached”
Is this a known limitation or sensitivity of the built-in Modified Cam Clay model in FLAC3D during staged construction?
Is there a recommended way to initialize MCC zones during lift placement to avoid yield surface incompatibility?
I would appreciate any guidance or examples of stable workflows for staged embankment construction using MCC (especially with later unsaturated coupling).
Additionally, if a more appropriate approach is to implement a fully coupled unsaturated constitutive model using FISH, I would greatly appreciate guidance or examples on how to structure such a zone-by-zone constitutive update within FLAC3D.